Ajnara & Gulshan Homz: Timely payment but Still pay Interest on delayed payment

Would like to share my case with Ajnara & Gulshan Homz

Please watch out for other builders, if you are buying in pre-launch, i.e. the projects is not approved by Authority, NOIDA in my case. Once it gets approved by authority, then builder has to prepare all the legal documents after which Bank approves the project for the loans.

November, 2009Made first payment towards booking.
January 14, 2010The date on the allotment letter. We signed it little later though, they changed the date. (that's the biggest mistake on our side)
January 27, 2010Project gets approved by NOIDA
March, 2010Project gets approved by IDBI bank. First bank to approve.
March 17, 2010Demand letter for next installment. 85% in my case of Down Payment.
March 18, 2010Bank issues the loan & the cheque
March 19, 2010Cheque is submitted to the AGC and receipt has been received.

Now they have added interest on 85% of the total flat cost for not sure how many months, which they think its been delayed.

Approval letter from Noida for Homes 121, Ajnara & Gulshan Homz
Charging interest even though project wasn't approved by Noida or the bank
Ajnara & Gulshan homz extorting money from the buyers on the name of interest on delayed payment.
Demand letter with no mention of any interest whatsoever.
Ajnara & Gulshan homz extorting money from the buyers on the name of interest on delayed payment.
Receipt from Ajnara & Gulshan within 2 days from Demand Letter


The haven't intimidated for the next payment, no demand letter or anything before March as they were claiming.

"Sir, dont worry we wont ask for the payment until unless its get approved by the bank."

That's the story three years back. They don't care about anything now. As per the allotment letter, you must have paid in full and, above all, we have signed the legal document.

That was all just DO NOT trust on their words,
  1. Its all OK to make booking in pre-launch.
  2. We won't charge any penalty until bank approves the project.
  3. We will send you the demand letter then only you have to make the payment.



We have suffered, just keep an eye all sorts of promises these builder make at the time when they need money from us and they forget everything when you are stuck with them.